Skip to main content
File #: 19-0949    Version: 1 Name:
Type: Release of Security Status: Passed
File created: 10/24/2019 In control: City Council
On agenda: 11/6/2019 Final action: 11/6/2019
Title: City Council consideration of releasing the Public Improvement Securities associated with the Bedford Canyon Water Line, Tract Map 36294 - Arantine Hills Holdings LP, a Delaware Limited Partnership.
Attachments: 1. Staff Report, 2. Exhibit A - Location Map

AGENDA REPORT

REQUEST FOR CITY COUNCIL ACTION

 

 

 

DATE:                                          11/06/2019

 

TO:                                          Honorable Mayor and City Council Members

                     

FROM:                     Public Works Department

 

SUBJECT:                     

Title

City Council consideration of releasing the Public Improvement Securities associated with the Bedford Canyon Water Line, Tract Map 36294 - Arantine Hills Holdings LP, a Delaware Limited Partnership.

 

End

RECOMMENDED ACTION:

Recommended action                     

That the City Council release the Public Improvement Securities associated with the Bedford Canyon Water Line, Tract Map 36294 (PB02479500550).

 

Body

ANALYSIS:

Tract Map 36294 is a multi-phase subdivision of 276 acres, approved by the City Council on June 28, 2017.  The project is located south of Eagle Glen Parkway and west of Interstate 15, as shown on Exhibit “A,” and is comprised of a master-planned residential community including a general commercial development.  The developer proposes to construct a maximum of 1,806 dwelling units and 80,000 square-feet of general commercial. On June 28, 2017, Arantine Hills Holdings LP entered into an improvement agreement with the City and posted security to guarantee construction of the Bedford Canyon Water Line.

The City of Corona has constructed the Bedford Canyon Water Line and the Arantine Hills Developer has paid the City the full cost to construct the water facilities in accordance with the Arantine Hills Development Agreement.  Therefore, it is appropriate to release, in full, the Faithful Performance and Labor and Material Securities for the Bedford Canyon Water Line at this time.

 

COMMITTEE ACTION:

Not applicable.

 

STRATEGIC PLAN:

Not applicable.

 

FISCAL IMPACT:

All applicable fees have been paid by the developer.

 

ENVIRONMENTAL ANALYSIS:

This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the general rule that CEQA applies only to projects that have the potential for causing a significant effect on the environment.  Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA.  This action merely releases the current security associated with a ministerial permit.  Since there is no possibility that adopting this action will have a significant effect on the environment, no environmental analysis is required.

 

PREPARED BY: MICHELE HINDERSINN, P.E., SENIOR CIVIL ENGINEER

 

REVIEWED BY: TOM KOPER, P.E., ACTING PUBLIC WORKS DIRECTOR

 

REVIEWED BY: KERRY D. EDEN, ASSISTANT CITY MANAGER/ADMINISTRATIVE SERVICES DIRECTOR

 

REVIEWED BY: MICHELE NISSEN, ASSISTANT CITY MANAGER

 

SUBMITTED BY: MITCHELL LANSDELL, INTERIM CITY MANAGER

 

Attachments:

1.                     Exhibit “A” - Location Map

 

 Owner:                       Arantine Hills Holdings LP

                                          85 Enterprise, Suite 450

                                          Aliso Viejo, CA 92656

                                          Attn: John Sherwood

                                          (949) 382-7822

 

Engineer:                       Hunsaker & Associates

                                          2900 Adams Street

                                          Suite A-15

                                          Riverside, CA 92504