Title: City Council consideration to accept the Precise Grading and Public Improvements associated with 910 Ontario Avenue and release the appropriate Grading and Public Improvements Securities - Cirks Construction, Inc.

AGENDA REPORT

REQUEST FOR CITY COUNCIL ACTION

 

 

 

 

DATE:                                          7/5/2018

 

TO:                                          Honorable Mayor and City Council Members

                     

FROM:                     Public Works Department

 

SUBJECT:                     

Title

City Council consideration to accept the Precise Grading and Public Improvements associated with 910 Ontario Avenue and release the appropriate Grading and Public Improvements Securities - Cirks Construction, Inc.

 

End

RECOMMENDED ACTION:

Recommended action                     

That the City Council accept the Grading and Public Improvements associated with 910 Ontario Avenue, and take the following actions:

 

1.                     Retain 25 percent of the Faithful Performance Security for one (1) year beyond the acceptance of the improvements as security for repair or replacement of any improvements that fail to meet City Standards at the end of the one-year period (RCB006177, RCB006184).

 

2.                     Retain the Labor and Material Security for six (6) months beyond the acceptance of the improvements, and automatically release the security unless any claims are filed (RCB006177, RCB006184).

 

3.                     Release the Precise Grading and Erosion Control Securities (RCB006176 and DEP16-0104).

 

Body

ANALYSIS:

On August 3, 2016, the City entered into Precise Grading and Public Improvement Agreements with Cirks Construction, Inc. to secure the precise grading and public improvements associated with 910 Ontario Avenue. The owner leased the property to Halferty Development Company, who constructed a 16,124 square-foot drive-through pharmacy in the C-3 General Commercial Zone. 

 

Also, on April 5, 2017, the City entered into a Public Improvement Agreement with Cirks Construction, Inc. to secure construction of the required off-site public landscaping improvements.

 

All of the precise grading and public improvements secured by these agreements have been completed and inspected to City specifications.

 

Twenty-five percent of the Faithful Performance Security will be retained for a period of one (1) year to guarantee repair or replacement of any improvements that fail prior to the end of the one-year period. Any written claims against the performance security must be made prior to the one-year guarantee period, which is set to expire July 5, 2019. City staff must release the Faithful Performance Security one (1) year after acceptance of the improvements by the City Council, pursuant to California Government Code Section 66499.9 (c). 

 

It is necessary to retain the Labor and Material Security for a period of six (6) months, in accordance with the State Subdivision Map Act. 

 

The site has been precise graded in accordance with all City Standards and the approved Precise Grading Plan. Therefore, it is appropriate to release the Precise Grading and Erosion Control Securities at this time.

 

COMMITTEE ACTION:

Not applicable.

 

STRATEGIC PLAN:

Not applicable.

 

FISCAL IMPACT:

All applicable fees have been paid by the developer. It is the City’s responsibility to begin the maintenance of the public improvements one (1) year after the date of acceptance.  The owner will be responsible for maintenance of the landscaping within the City rights-of-way fronting the project. 

 

ENVIRONMENTAL ANALYSIS:

This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the general rule that CEQA applies only to projects that have the potential for causing a significant effect on the environment.  Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. This action merely releases the current securities associated with the property. Since there is no possibility that adopting this action will have a significant effect on the environment, no environmental analysis is required.

 

 

PREPARED BY: MICHELE HINDERSINN, P.E., SENIOR CIVIL ENGINEER

 

REVIEWED BY: TOM KOPER, P.E., ASSISTANT PUBLIC WORKS DIRECTOR

 

REVIEWED BY: NELSON D. NELSON, P.E., PUBLIC WORKS DIRECTOR

 

REVIEWED BY: KERRY D. EDEN, ASSISTANT CITY MANAGER/ADMINISTRATIVE SERVICES DIRECTOR

 

SUBMITTED BY: DARRELL TALBERT, CITY MANAGER

 

 

Owner:                                          Ontario & Buena Vista Associates, LLC, 205 Savona Walk, Long Beach, CA 90803

                                          

Engineer:                      KWC Engineers, 1880 Compton Avenue, Suite 100, Corona, CA 92881