Title: CONSTRUCTION CONTRACT TO R C FOSTER CORPORATION FOR LESTER POST DISINFECTION STATION NO. UT-2013-02; NOTICE INVITING BIDS 24-071CA
Attachments: 1. Staff Report, 2. Exhibit 1 - Location Map, 3. Exhibit 2 - Construction Contract
REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION



DATE: 06/05/2024

TO: Honorable Mayor and City Council Members
Honorable President and Board Members

FROM: Public Works Department

SUBJECT:
Title
CONSTRUCTION CONTRACT TO R C FOSTER CORPORATION FOR LESTER POST DISINFECTION STATION NO. UT-2013-02; NOTICE INVITING BIDS 24-071CA

End
EXECUTIVE SUMMARY:
This staff report asks for the City Council to approve the construction contract with R C Foster Corporation. The project encompasses constructing new steel piping and a cast-in-place open-top concrete vault with a new magnetic meter, static mixer, and chlorine & ammonia injection downstream from the Lester Plant filters.

RECOMMENDED ACTION:
Recommended action
That the City Council:

a. Approve the Construction Contract with R C Foster Corporation for the Lester Post Disinfection Station, Project No. UT-2013-02 in the amount of $1,849,500.

b. Adopt the Plans and Specifications for the Lester Post Disinfection Station, Project No. UT-2013-02, Notice Inviting Bids 24-071CA.

c. Award Notice Inviting Bids 24-071CA to R C Foster Corporation, the lowest responsive, responsible bidder, for the total bid amount of $1,849,500 and waive any and all minor irregularities in the bidding documents as submitted by said bidder.

d. Authorize the City Manager, or his designee, to execute the with R C Foster Corporation in the amount of $1,849,500, including any non-substantive extensions, change orders, purchase orders, and amendments up to the amount equivalent to 10% or $184,950.

That the Corona Utility Authority review, ratify, and, to the extent necessary, direct the City Council to take the above actions

Body
BACKGROUND & HISTORY:
This project will relocate the post-disinfection injection point onto the 30" filter effluent line between filters and the Chlorine Contact Basin and install two injectors. By completing this CIP, filters 5 and 6 can run independently, which they cannot do in the ...