REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION
DATE: 01/17/2024
TO: Honorable Mayor and City Council Members
Honorable President and Board Members
FROM: Utilities Department
SUBJECT:
Title
MAINTENANCE/GENERAL SERVICES AGREEMENT WITH VALVERDE CONSTRUCTION INC. FOR CRITICAL WATER MAIN REPLACEMENT ON RIDGEVIEW TERRACE
End
EXECUTIVE SUMMARY:
This staff report asks City Council to approve a Maintenance/General Services Agreement with Valverde Construction, Inc. for a critical water main replacement project on Ridgeview Terrace, a section on Via Santiago, and four cul-de-sac sections adjacent to Ridgeview Terrace.
RECOMMENDED ACTION:
Recommended action
That the City Council:
a. Award the Maintenance/General Services Agreement with Valverde Construction, Inc., of Santa Fe Springs, CA, in the amount of $1,894,157 to perform critical water main replacement on Ridgeview Terrace, a section on Via Santiago and four cul-de-sac sections adjacent to Ridgeview Terrace.
b. Authorize the City Manager, or his designee, to execute a Maintenance/General Services Agreement with Valverde Construction, Inc., for a total contract amount of $1,894,157, including non-substantive extensions, purchase orders, change orders and amendments up to $100,000, as authorized in Corona Municipal Code Section 3.08.060(J).
c. Authorize the creation of a new Capital Improvement Project titled "Ridgeview Terrace Water Main Installation."
d. Authorize an appropriation in the amount of $1,994,157 from the Water Utility Fund 570 to the newly created Ridgeview Terrace Water Main Installation Capital Improvement Project.
That the Corona Utility Authority review, ratify, and to the extent necessary, direct that the City Council take the above actions.
Body
BACKGROUND & HISTORY:
The Utilities Department (UD) infrastructure division is responsible for operating and maintaining the City of Corona's extensive network that comprises, operates, and maintains approximate...