File #: 24-0615    Version: 1 Name:
Type: Agreement Status: Passed
File created: 7/30/2024 In control: City Council
On agenda: 8/21/2024 Final action: 8/21/2024
Title: APPROVAL OF THE BEDFORD CHANNEL EXTENSION PUBLIC IMPROVEMENT AGREEMENT AND SECURITY FOR TRACT MAP 38572 LOCATED SOUTHWEST OF CLEMENTINE WAY AND HUDSON HOUSE DRIVE (APPLICANT: ARANTINE HILLS HOLDINGS LP, A DELAWARE LIMITED PARTNERSHIP)
Attachments: 1. Staff Report, 2. Exhibit 1 - Location Map, 3. Exhibit 2 - Agreement
REQUEST FOR CITY COUNCIL ACTION



DATE: 08/21/2024

TO: Honorable Mayor and City Council Members

FROM: Planning and Development Department

SUBJECT:
Title
APPROVAL OF THE BEDFORD CHANNEL EXTENSION PUBLIC IMPROVEMENT AGREEMENT AND SECURITY FOR TRACT MAP 38572 LOCATED SOUTHWEST OF CLEMENTINE WAY AND HUDSON HOUSE DRIVE (APPLICANT: ARANTINE HILLS HOLDINGS LP, A DELAWARE LIMITED PARTNERSHIP)

End
EXECUTIVE SUMMARY:
This staff report asks the City Council to approve the public improvement security agreement between the City of Corona and Arantine Hills Holdings LP, a Delaware Limited Partnership for the design, construction, inspection, acceptance, operation and maintenance of the Bedford Canyon Channel, Stage 2 storm drain facilities and related maintenance access roads.

RECOMMENDED ACTION:
Recommended action
That the City Council authorize the Mayor to execute the Bedford Channel Extension Improvement Agreement for Tract Map 38572 between the City and Arantine Hills Holdings LP, a Delaware Limited Partnership.

Body
BACKGROUND & HISTORY:
The Bedford Community is a 325.7-acre master-planned residential and commercial development located on the west side of Interstate 15 and south of Eagle Glen Parkway. The community is being completed in phases per the zoning and development standards established by the Arantine Hills Specific Plan. TTM 38572, known as Phase 3 and 4 of Bedford, was approved by the City Council on April 3, 2024, and will facilitate the development of 546 attached and detached condominium homes and 50 lettered lots for the construction of private streets, open space, private parks, trails and the extension of the Bedford Channel identified as Lot P.
The City and the District entered a Cooperative Agreement on October 17, 2018, for the Arantine Hills Bedford Canyon Wash Stage 1 and the Levee Stage 1 improvements. The construction associated with the Stage 1 wash improvements was completed simultaneously with the development of Phase 1 of...

Click here for full text