REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION
DATE: 12/07/2022
TO: Honorable Mayor and City Council Members
Honorable President and Board Members
FROM: Public Works Department & Utilities Department
SUBJECT:
Title
Award of Contract to MNR Construction, Inc. for the Wardlow Road Sewer Relocation Project No. 2017-18.
End
EXECUTIVE SUMMARY:
This staff report asks the City Council to award a construction contract to MNR Construction, Inc. to improve the sewer facilities at Wardlow Road and address sewer deficiencies from the Sierra Del Oro (SDO) sewer shed to the Water Reclamation Facility #1 (WRF-1). The Wardlow Sewer Relocation Project will replace and upsize the existing 18" gravity sewer main line to 24" located under State Route 91 and on the Allsize Storage Corona (Allsize) property to accommodate future commercial and residential projects in the SDO area.
RECOMMENDED ACTION:
Recommended action
That the:
a. City Council adopt the Plans and Specifications for the Wardlow Road Sewer Relocation Project, Project No. 2017-18, Notice Inviting Bids 23-016CA.
b. City Council award Notice Inviting Bids 23-016CA to MNR Construction, Inc., the lowest responsive, responsible bidder, for the total bid amount of $2,357,980, and waive any and all minor irregularities in the bidding documents as submitted by said bidder.
c. City Council authorize the City Manager, or his designee, to execute the construction contract with MNR Construction, Inc. in the amount of $ 2,357,980.
d. City Council authorize the City Manager, or his designee, to negotiate and execute non-substantive extensions, change orders, and amendments up to the amount authorized in Corona Municipal Code Section 3.08.060(J), which is equivalent to 10% or $235,798.
e. City Council authorize the issuance of a Purchase Order to MNR Construction, Inc. in the amount of $2,357,980 for construction services.
f. City Council authorize an appropriation in the amount of $1,491,37...