Title: City Council and Corona Utility Authority consideration of approving Contract Change Order No. 2 for construction of the Corona Airport Waterline Relocations Project, No. 2018-01, approve budget reductions in the Water Utility and Reclaimed Water Utility Funds, and approve a General Fund appropriation of $185,334.
Attachments: 1. Staff Report, 2. Staff Report with Attachments
AGENDA REPORT
REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION




DATE: 2/6/2019

TO: Honorable Mayor and City Council Members
Honorable President and Board Members

FROM: Public Works Department
Department of Water and Power

SUBJECT:
Title
City Council and Corona Utility Authority consideration of approving Contract Change Order No. 2 for construction of the Corona Airport Waterline Relocations Project, No. 2018-01, approve budget reductions in the Water Utility and Reclaimed Water Utility Funds, and approve a General Fund appropriation of $185,334.

End
RECOMMENDED ACTION:
Recommended action
That the:

1. City Council approve Contract Change Order No. 2 in the amount of $67,405.14 to J.R. Filanc Construction Company, Inc., the contractor constructing the Corona Airport Waterline Relocations Project, No. 2018-01.

2. City Council authorize the City Manager to execute Contract Change Order No. 2 to the existing Contract between the City and J.R. Filanc Construction Company, Inc.

3. City Council authorize the Purchasing Manager to issue Change Order No. 2 to Purchase Order P20978 to J.R. Filanc Construction Company, Inc., in the amount of $67,405.14, for a total amount of $499,325.81, which represents a cumulative total construction cost increase of 20.34 percent.

4. City Council approve a budget reduction in the amount of $160,334.13 from the Corona Airport Waterline Project in the Water Utility Fund 570.

5. City Council approve a budget reduction in the amount of $25,000.00 from the Corona Airport Waterline Project in the Reclaimed Water Utility Fund 567.

6. City Council approve an appropriation of $185,334.13 to the Corona Airport Waterline Project in the General Fund 110.

7. Corona Utility Authority (CUA) review, ratify, and to the extent necessary, direct that the City Council take the above actions.

Body
ANALYSIS:
The Corona Airport Waterline Project design was initiated in 2011 in response to the U....