File #: 19-1013    Version: 1 Name:
Type: Reports Status: Passed
File created: 11/20/2019 In control: City Council
On agenda: 12/4/2019 Final action: 12/4/2019
Title: City Council consideration to terminate the emergency action for Contracted Emergency Repair Work for Fire Station #1 pursuant to Corona Municipal Code (CMC) 3.08.130(A).
Attachments: 1. Staff Report, 2. Exhibit A - Emergency Repairs at Fire Station 1

AGENDA REPORT

REQUEST FOR CITY COUNCIL ACTION

 

 

 

DATE:                                          12/04/2019

 

TO:                                          Honorable Mayor and City Council Members

                     

FROM:                     Maintenance Services

 

SUBJECT:                     

Title

City Council consideration to terminate the emergency action for Contracted Emergency Repair Work for Fire Station #1 pursuant to Corona Municipal Code (CMC) 3.08.130(A).

 

End

RECOMMENDED ACTION:

Recommended action                     

That the City Council terminate the emergency action for Contracted Emergency Repair Work for Fire Station #1 located at 540 Magnolia Avenue.

 

Body

ANALYSIS:

On November 6, 2019, City Council received the notification of contracted emergency work for Fire Station #1 located at 540 Magnolia Avenue and authorized a one-time appropriation of $60,000 from General Fund 110 to Maintenance Services’ operating budget for mold remediation and plumbing repairs utilizing the Exception to Competitive Bidding provision for emergency repairs pursuant to Corona Municipal Code (“CMC”) Section 3.08.130(A).

On September 24, 2019, the firefighters at Station #1 reported to the Maintenance Services Department (MSD) that a water leak had occurred due to a leaking water pipe connecting the washing machine. The water damage exposed substantial mold throughout the wall in the laundry space and the bathroom which shares the wall.  The extensive mold required removal of all the bathroom sinks and two wall urinals.  Since this is a facility housing emergency personnel who operate 24-hour shifts, the mold remediation is a top priority.

The following table shows list of repairs, services and tasks provided by different contractors and associated percent of completion. 

 

The emergency repair and project update were provided to the City Council on November 20, 2019. The emergency repairs and the project are completed at this time. In accordance with CMC Section 3.08.130 requirements, City Council shall terminate the emergency action now that all emergency repairs have been completed. Emergency repair and project pictures are attached in Exhibit A.

 

COMMITTEE ACTION:

Not applicable.

 

STRATEGIC PLAN:

Not applicable.

 

FISCAL IMPACT:

There were no additional fiscal impacts beyond the cost of repairs approved by the City Council on November 6, 2019.

 

ENVIRONMENTAL ANALYSIS:

No environmental review is required because the proposed action is not a project governed by the California Environmental Quality Act.

 

PREPARED BY: aftab hussain, maintenance manager

 

REVIEWED BY: katie hockett, assistant general manager

 

REVIEWED BY: tom moody, general manager

 

REVIEWED BY: scott briggs, purchasing specialist V

 

REVIEWED BY: KIM SITTON, ACTING ADMINISTRATIVE SERVICES DIRECTOR

 

SUBMITTED BY: JACOB ELLIS, CITY MANAGER

 