AGENDA REPORT
REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION
DATE: 03/18/2020
TO: Honorable Mayor and City Council Members
Honorable President and Board Members
FROM: Public Works Department
Department of Water and Power
SUBJECT:
Title
City Council and Corona Utility Authority consideration of the Third Amendment to the Professional Services Agreement between the City and Moraes/Pham & Associates and approve Contract Change Order No. 1 for the construction phase of electrical engineering services for the Garretson Blend Station Zone 3 Emergency Generator, Project No. 2019-05.
End
RECOMMENDED ACTION:
Recommended action
That the:
a. City Council approve Contract Change Order No. 1 in the amount of $15,000.00 to Moraes/Pham & Associates, the electrical design engineer for the Garretson Blend Station Zone 3 Emergency Generator (Project), Project No. 2019-05.
b. City Council authorize the Department of Water and Power General Manager to execute the Third Amendment to the existing Professional Services Agreement (PSA) between the City and Moraes/Pham & Associates.
c. City Council authorize the Purchasing Manager to issue Change Order No. 1 to Purchase Order R171702 to Moraes/Pham & Associates in the amount of $15,000.00 for a total of $41,202.00.
d. Corona Utility Authority (CUA) review, ratify, and to the extent necessary, direct the City Council to take the above actions.
Body
ANALYSIS:
The Project will construct new emergency generator facilities at the Garretson Blend Station to equip the 1060-Zone booster pump station with a 1000kW standby power generator. The Project is located on City-owned property at the southeast corner of East Ontario Avenue and Magnolia Avenue within the Garretson Blend Cell site. The Garretson Blend Cell is a key component of the City's potable water distribution system and one of two facilities used to blend groundwater with treated potable water. Continued operation of the Garr...